You have created an Excel spreadsheet that shows cumulative cost at any particular point of time in the project duration. Your director wants to review the project costs and you decide to make a presentation. Cumulative cost plotted against time is shown in the slide as?
A、S-curve.
B、Histogram.
C、Control chart.
D、Pareto chart.