After reviewing the project schedule, the project manager realizes that a unique resource on a specific activity on the critical path will not be released on time, but will be available at a later date. What should the project manager do next ?
A、Work with the critical path method
B、Ask management for resources
C、Define activity resource requirements
D、Apply the critical chain method