久久aa|国产精品免费一区二区三区在线观看|久久精品色|欧美色亚洲,封神英雄72集完整版在线观看 ,钟丽缇色戒完整版在线看,国产精品成人一区二区三区夜夜夜

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(7)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(7)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During project executing, one of the electrical engineers informs the project manager that the life cycle cost of the new heating and air conditioning system is higher than the life cycle cost of another heating and air condition system. What should the project manager do?
A、Determine if there is room in the project budget for the additional cost.
B、Select the product with the lower life cycle cost.
C、Select the product with the best life cycle cost to earned value ratio.
D、Select the product with the lowest maintenance cost to life cycle cost ratio.


相關試題

推薦文章
合作網(wǎng)站內(nèi)容